Risk Module — Overview
The Risk module is the project's risk register. Each risk records what could go wrong, how bad it would be (Impact), how likely it is (Probability), who owns it, and what is being done about it.
The module is web-only — there is no mobile version.
You will find it in the Tracking group of the navigation sidebar.

Rating
AECIS calculates each risk's Rating from its Impact and Probability. Each level scores 1 to 5, and the rating score is their product:
| Impact | Score | Probability | Score |
|---|---|---|---|
| Insignificant | 1 | Very Low (0–20%) | 1 |
| Minor | 2 | Low (20–40%) | 2 |
| Moderate | 3 | Medium (40–60%) | 3 |
| Major | 4 | High (60–80%) | 4 |
| Severe | 5 | Very High (80–100%) | 5 |
The rating badge shows a band and the score:
| Band | Score |
|---|---|
| INSIGNIFICANT | 1–4 |
| MINOR | 5–9 |
| MODERATE | 10–12 |
| MAJOR | 15–16 |
| SEVERE | 20–25 |
For example, a Major impact with Medium probability is MODERATE · 12.
The list
| Control | What it does |
|---|---|
| + New | Opens the New Risk panel |
| Search box | Filters by risk name or number |
| Filter | Filters by Rating, Creator, Package, Discipline, Probability, Impact, Owner, Assignee, DTag, Action Date, Created and Last Activity Date. Tick values and click Apply; Clear all resets |
| Export (download icon) | PDF report (Risk Analysis Report) or Excel, for the current filtered list — works as in the Issue list |
| Manage Columns (panel icon) | Show, hide and reorder columns |
Default columns: No, Name, Rating, Impact, Probability, Owner, Package, Discipline, Action Date, Date Raised, Creator, Last Activity Date. More are available: Assignee, Consequence, Likelihood, Current Control, Further Treatment.
The footer shows how many risks are loaded, e.g. "Showing 50 of 137"; scroll down to load more. Click a row to open the risk detail.